What happened

39 metres of the Coliban Main Channel were severely damaged in the wet weather event.


How we're building back better.

Our contractors began restoration works on 1 November 2022 and completed works on Monday 5 December 2022.

We upgraded the track alongside the channel to improve accessibility during emergencies.

We installed a temporary fix for two weeks to ensure security of supply to Bendigo while repairs were undertaken.

Coliban Main Channel

Repairs to the Coliban Main Channel