We are undertaking extensive repairs and rectification works to the Elmore Water Tower.

The project is needed to maintain a long-term secure water supply to Elmore, and improve pressure experienced by customers.

The project will take several years and be completed in 3 phases at a total cost of $1.1 Million

If you have any questions, please contact our Customer Support Team on 1300 363 200.

Timeline

  • Timeline item 1 - complete

    Phase One

    Will include extending the fence line, burying the storm water drain onsite, preparing a hard stand for ground level tank and extending the sewer to the water treatment plant. August 2021.

  • Timeline item 2 - active

    Phase two

    This phase will involve increasing the water storage capacity by building three, 50 KL ground-level tanks and a booster pump station to maintain town pressure while the elevated tank is taken offline for repair works. Works will start in May 2022 and the planned commissioning date is late June 2022.

  • Timeline item 3 - incomplete

    Phase Three

    Our final phase will involve rehabilitating the existing elevated storage tank.

Elmore water tower